The US 287 Resurfacing and Roadway Improvements Project - Update 1.9.23-1.13.23
The US 287 Resurfacing and Roadway Improvements project continues to make progress. Traffic continues to be reduced to single-lane head-to-head configuration. Your patience is appreciated as we work to improve this section of the roadway.
Work the week of January 9 - 13
Work next week includes shoulder paving, curb and gutter paving, and ADA curb ramp paving. The following are impacts for the upcoming week to be aware of:
Traffic has shifted and motorists are now into a head-to-head configuration on the southbound side of the roadway from Laurel Street to Savage Avenue (traffic will remain in this configuration through winter 2023).
- Westbound road closures remain in place at Parkway Drive, Forrest Street, Lynn Street, and Savage Avenue
- Motorists can expect minor delays as flaggers guide equipment in and out of the work zone.
Travel Impacts
- Monday - Friday, January 9 - 13, from sunup to sundown, minor delays can occur
- 11-foot lane restrictions in place 24/7
- Side street detours
- Detours at various sidewalks are in place
- Delays at intersections are possible as construction equipment moves in and out of the work areas
- Business access will be maintained during construction. Please obey all construction zone speed limits
See the detour map below, to access east-side businesses.